Plant Maintenance SOPs
Maintenance Summary SOPsPlant Maintenance Department
1. Breakdown Maintenance ๐ง Detailed Steps:
- 1. Technician logs the breakdown in the daily report during production.
- 2. If repair or replacement is needed, a Material Request Form (MR) is prepared.
- 3. Supervisor reviews the MR to confirm actual requirement.
- 4. MR is sent to (Maintenance Manager) for approval.
- 5. Storekeeper verifies item availability and issues the spare, if unavailable storekeeper inform Maintenance Manager.
- 6. Technician performs the repair or installation and records everything in the Job Record.
- 7. Supervisor and QC review and verify the work.
- 8. Maintenance Manager gives final approval after reviewing all documentation.
- 9. If breakdown exceeds 30 minutes, an RCA report is prepared.
- ๐ Documents:
- Daily Breakdown Report, Material Request Form, Maintenance Job Record, RCA Report
- ๐ฅ Roles:
- Technician, Supervisor, Storekeeper, Quality Checker, Maintenance Manager
- ๐ผ Accounting Impact:
- Spare issuance is recorded as consumption expense in ERP.
- ๐๏ธ Source: Plant Maintenance SOP 210325
2. Preventive Maintenance ๐ง Detailed Steps:
- 1. Technician and operator perform daily checks using designated checklists.
- 2. CLTI Form (Cleaning, Lubrication, Tightening, Inspection) is filled.
- 3. If fault found, process continues as Breakdown or External Repair.
- 4. Monthly preventive maintenance is scheduled alongside weekly production plan.
- 5. Detailed Monthly Checklist used for each machine.
- 6. If same equipment receives repeated service >40 days, escalate to Maintenance Manager and Product Manager to take a decision.
- 7. After service, supervisor reviews and signs off.
- 8. QC verifies quality before final closure.
- ๐ Documents:
- Daily Checklist, Monthly Preventive Checklist, CLTI Form, Job/Site Report
- ๐ฅ Roles:
- Technician & Operator, Supervisor, Maintenance Manager, Quality Checker
- ๐ผ Accounting Impact:
- Spare usage is recorded as expense in ERP upon issuance. Overhauling Details in Point No. 6
- ๐๏ธ Source: Plant Maintenance_Final SOP 210325 External Repair in Point No. 7
3. Spares Management ๐ง Detailed Steps:
- Storekeeper prepares monthly inventory report.
- Good Receipt Note (GRN) entries, consumption, and adjustments are verified in ERP.
- Safe stock limits are reviewed.
- If breached, Purchase Requisition (PR) is raised.
- If not breached, report shared with Supervisor for review.
- Supervisor evaluates and escalates to Maintenance Manager.
- Maintenance Manager approves or suggests revision.
- Upon approval, initiate either:
- Regular Purchase
- Non-PO urgent procurement
- Safe stock limits updated in ERP as required.
- ๐ Documents:
- Inventory Report, GRN Records, Purchase Requisition
- ๐ฅ Roles:
- Storekeeper, Supervisor, Maintenance Manager
- ๐ผ Accounting Impact:
- No accounting impact unless spares are issued.
- ๐๏ธ Source: Plant Maintenance SOP
4. Vendor Service Management ๐ง Detailed Steps:
- Supervisor maintains an Annual Maintenance Contract (AMC) Tracker with contract/service schedule data.
- Start of each month: upcoming services are reviewed and vendor notified.
- Vendor is reminded 1 week in advance with equipment and service details.
- On arrival: vendor logs in at security and complies with safety protocols.
- Service is executed as per AMC terms and monitored by maintenance team.
- Issues or notes are logged and followed up.
- After service: Service Report is signed by vendor, Supervisor, and QC (if needed).
- AMC Tracker updated and shared with Accounts for processing.
- ๐ Documents:
- AMC Tracker, Service Confirmation Report
- ๐ฅ Roles:
- Supervisor, Vendor, QC (if applicable), Security, Accounts
- ๐ผ Accounting Impact:
- Service expense recorded upon invoice receipt or provision.
- ๐๏ธ Source: Plant Maintenance SOP
5. Employee Training Program ๐ง Detailed Steps:
- Maintenance Manager prepares an annual training plan based on skill gaps, new tech, and safety practices.
- Trainings scheduled for the year.
- Topics include CLTI, breakdown handling, spare management, safety.
- Event-based trainings conducted for new equipment or changes.
- New technicians are trained before operational deployment.
- Training includes theory, practice, and workshops.
- Attendance is logged, performance evaluated, and records maintained.
- ๐ Documents:
- Training Agenda, Attendance Log, Feedback Forms
- ๐ฅ Roles:
- Maintenance Manager, Supervisor, HR, Maintenance Staff
- ๐ผ Accounting Impact:
- Internal administrative cost; not booked as direct expense.
- ๐๏ธ Source: Plant Maintenance SOP
6. Overhauling ๐ง Detailed Steps:
- Annual overhaul schedule created for off-season.
- Includes critical equipment needing cleaning, replacement, or alignment.
- List shared with Plant Manager for review.
- If cost exceeds budget, requires PM + Accounts approval.
- Maintenance executed and QC inspected before restart.
- ๐ Documents:
- Overhaul Plan, Approval Notes, QC Checklist
- ๐ฅ Roles:
- Maintenance Head, Plant Manager, Quality Checker
- ๐ผ Accounting Impact:
- Capitalized if cost >40% of asset value; else expensed.
- ๐๏ธ Source: Plant Maintenance SOP
7. External Repairs ๐ง Detailed Steps:
- If in-house repair is not possible, part is dismantled.
- Repair Request raised and ERP Gate Pass issued.
- Security stamps Gate Pass before part leaves.
- Vendor performs repair externally.
- On return, part is reinstalled and QC verifies.
- Invoice is booked as expense.
- ๐ Documents:
- Repair Request, Gate Pass, Vendor Invoice, QC Form
- ๐ฅ Roles:
- Technician, Supervisor, Storekeeper, QC, Vendor
- ๐ผ Accounting Impact:
- Repair expense recorded upon invoice.
- ๐๏ธ Source: Plant Maintenance SOP